What is commissioning?

Commissioning is a quality-oriented process in which the requirements for actual performance of a building system are prescribed. In this process, the actual performance of the system is checked against the requirements and other norms at the time of design of a newly-constructed building, or during the normal operation of an existing building. The verification results are recorded, and improvement action is taken if any discrepancy is identified.
Commissioning may be categorized largely into two types: initial commissioning, which is conducted for a newly-constructed building, and retro-commissioning, which is the first commissioning performed for an existing building. Beyond these, continuous commissioning is provided from time to time as part of normal building management.
Alephnet is focused on retro-commissioning and continuous commissioning. We often combine our commissioning services with renewal planning for centralized monitoring and automatic control systems.
→What is commissioning?

このページの先頭へ

Commissioning specialists

 We are a supporting member of the Building Services Commissioning Association (BSCA),
with 1 CxPE-certified specialist and 2 CxTE-registered specialists.
 →BSCA HP CxPE・CxTE

このページの先頭へ

Features and strengths of our commissioning services

- Analysis of BEMS data and detection of faults

- Automatic setting tuning and control-improvement based on analysis results (low-cost energy-saving measures)

→As a builder of SCADA systems, BEMSs, and automatic control systems, we generally perform retro-commissioning at the time of system renewal.

- On-site measuring and data compilation

[Targets]

  • Buildings: Existing institutional-use buildings (schools, hospitals, hotels)
  • Air-conditioning systems: non-thermal storage two-/one-pump type heatl source systems, chilled/hot water storage-type air-conditioning systems,individual air-conditioning system (EHPs, GHPs)

[Chance for implementation]

  • The opportunity of renewing the centralized monitoring and automatic control system is approaching.
  • Renewal of heat source equipment is being considered.
  • Implementing energy- and electricity-saving measures is being considered.
  • The building has just been specified as Class II, or the customer has newly been designated as a subject of control under the revised Energy Saving Act.
  • Because the building has been designated as a control subject under the Energy Saving Act, preparation of building management standards and other documents is required.
    →Enhanced measuring is needed.

このページの先頭へ

List of past commissioning projects

No. Year of implementation Project name Details
1 2007-2008 Ritsumeikan University Biwako Kusatsu Campus (BKC)
Heat source equipment of Core Station
Retro-commissioning→Control-improvement→On-going-commissioning
2 2008-2010 Ritsumeikan University Biwako Kusatsu Campus (BKC)
Heat source equipment of Across Wing
Retro-commissioning→Control-improvement→On-going-commissioning
3 2009-2010 Ritsumeikan Uji Junior and Senior High School
Heat source equipment
Retro-commissioning→Control-improvement→On-going-commissioning
4 2006-2009 The Kansai Electric Power Co., Inc., Nuclear Business
Chilled/hot water storage-type air-conditioning system
Retro-commissioning→Control-improvement→On-going-commissioning
5 2006- Mukogawa Women's University Central Campus & Hama-Koshien Campus Retro-commissioning→On-going commissioning
6 2009-2010 Building Research Institute
Measurement service entrusted under the local air-conditioning verification project
FunctionalPerformanceTest: FTP  (on-site measurement and analysis)
7 2010-2011 Matsuzakaya Shizuoka Branch
Heat source equipment
Retro-commissioning→Auto control renewal in the heat source replacement→Initial-commissioning
8 2010 Kyoto University Yoshida Campus
Faculty of Engineering Radioisotope Research Laboratory
Retro-commissioning→On-going commissioning
9 2010 Ministry of Environment's subsidy project for diagnosing the potential for greenhouse gas reduction Retro-commissioning (analysis and proposal only)
10 2011-2013 Ritsumeikan Asia Pacific University (APU)
Heat source equipment
Retro-commissioning→Control-improvement→On-going-commissioning
11 2011-2013 Ritsumeikan University Biwako Kusatsu Campus (BKC)
Heat source equipment of Co-learning House I
Retro-commissioning→Control-improvement→On-going-commissioning
12 2011-2012 Ritsumeikan University Kinugasa Campus
Heat source equipment of Yoyokan Hall
Retro-commissioning→On-going commissioning
13 2011-2012 Kyoto Station Building Commissioning Project
On-site measurement and analysis for tenants
FunctionalPerformanceTest: FTP  (on-site measurement and analysis)
14 2012 Ritsumeikan University Biwako Kusatsu Campus (BKC)
Epoch Ritsumei 21 & Rohm Plaza
Air-conditioning equipment
Retro-commissioning
・Automation control system renewal in HVAC system renovation
15 May 2013 to March 2017 (as scheduled) Doshisha University Imadegawa Campus Ryoshin-kan Initial-commissioning
16 2013- Kyoto Station Building
Cold source systems
Retro-commissioning→Operation-improvement